This project will have four stages which will be centred around the four stages of the Development Plan process and the publication of four key documents.

Development Plan timeline

Stage 1

This is the Pre-Draft Stage and covers from week 1 to week 46. Key elements of this stage are:

  • March – May 2021: Public Consultation – Strategic Issues Paper
  • July 2021: Chief Executive Report on Consultation
  • September 2021: Directions from Elected Members to make a Draft Development Plan
  • October 2021 – February 2022: Preparation of Draft Development Plan

Stage 2

This is the Draft Development Plan Stage and covers weeks 47 – 82:

  • February – May 2022: Public Consultation on the Draft Development Plan
  • July 2022: Chief Executive Report on Submissions
  • October 2022: Consideration of Chief Executive Report by Elected Members

Stage 3

Material Amendments, this stage covers weeks 83 – 99

  • October 2022: Preparation of Material Amendments
  • November 2022: Public Consultation on Material Amendments
  • December 2022: Chief Executive Report on Submissions
  • January 2023: Consideration of Chief Executive Report by Elected Members

Stage 4

This is the final Phase and culminates with the making of the Development Plan by the Elected Members.

  • February 2023: Making of the Plan: The elected  members must pass a resolution to make  the plan.
  • March 2023: Plan Operational: The Plan becomes  effective 6 weeks following the passing of the  resolution by the elected members.